In the anti-corrosion construction of oil storage tanks, in order to ensure the safety of construction personnel and the quality of anti-corrosion construction, there are certain requirements for the environment of the construction site, especially for fire prevention. Below we have a detailed understanding.
1. The staff for anti-corrosion construction of oil storage tanks must undergo education and training on fire safety knowledge. Establish strict safety operation procedures and fire safety system, and check the implementation at any time, implement the reward and punishment system. To eliminate fire hazards in a timely manner, in addition to smoking outdoor, no smoking.
2. If open fire is required at the anti-corrosion construction site of the oil storage tank, the paint scale and combustible substances within 30 meters of the operation site shall be cleaned. Fixed painting equipment, conveyor belts, etc. shall be tightly covered with non-combustible materials.
3. The natural ventilation conditions of the construction site should be better. Strong ventilation and exhaust equipment should be set up in places with poor ventilation conditions, and the concentration of mixed gas should be determined at any time to prevent reaching the explosion concentration limit. In case of fire, the ventilation and exhaust equipment shall be shut down immediately.
4. It is forbidden to make fire for heating at the anti-corrosion construction site of oil storage tank. But can be steam, hot water, hot air and other methods of heating. Do not bake cotton fabrics on heating pipes, especially painted rags and gloves.
5. The construction site must be cleaned frequently to remove paint scale and combustibles at any time. Cotton yarn and dishcloth stained with paint shall be removed every day and shall not be littered. They shall be placed in a metal box filled with clean water and sealed with a cover. Work clothes with paint should be hung in a fixed and ventilated place. Work clothes should not be equipped with cloth and cotton yarn with paint to prevent nature.
6. The amount of paint and diluent used for one day is only allowed to be stored on the anti-corrosion construction site of the oil storage tank, and these paints cannot be placed at the door and where people often walk or operate. A safe place should be selected to properly place them, and the paint bucket should be covered to prevent solvent volatilization or burning in case of fire.